Position Reference DG0098
Position Title Independent Project Oversight Consultant
Closing Date November 12, 2009

Preamble

It is anticipated this engagement will continue through the completion of Phase VI (Deployment and Cutover) of the Client’s Project, currently scheduled for December 31, 2011.

In-state travel is not anticipated for this contract. In the event travel becomes necessary, the Client will compensate for travel costs as required in the completion of the assigned tasks. All travel costs will be reimbursed in accordance with the following:

bullet

Travel expenses will be charged utilizing current Client rates.

bullet

All travel will be approved by Client in advance of such travel.

Experience

Required Qualifications

The successful candidate for this position must have the following specific skills and experiences to assure project success:

bullet

Experience providing project management services for at one (1) applications development or COTS integration project having a one-time cost of not less than $10 million and a minimum of one-time development or integration lifecycle (per initial project schedule) of not less than 12 months.

bullet

Previous experience managing at least one large-scale integration project that included collaborative relationships with contracted IT development vendors.

bullet

At least 36 months of previous experience providing IPOC services on systems integration projects, at least one of which having a development and integration schedule lasting at least 24 months (per the initial schedule). Projects for where IV&V services were provided may be substituted for IPOC experience provided the contracted scope of the referenced engagement included project management oversight services.

bullet

Knowledge of and experience applying the CA IT Oversight Framework as of 2003 to a California government IT project with a one-time cost of at least $5 million.

bullet

Ability to effectively communicate orally and in writing with business and technical staff, and with all levels of management

bullet

Must provide a minimum of three (3) references for referenced projects.

Preferred Qualifications

The following specific skills and experiences are preferred for the successful candidate for this position:

bullet

Possession of a degree in information systems management or a valid PMP certificate.

bullet

Experience in a lead capacity on an applications development or COTS integration project involving external agencies or local governmental entities.

Scope of Work Summary

Contractor Responsibilities

The Contractor will provide independent project oversight services to the Client’s Project to meet the requirements of the IT Project Oversight Framework (as of 2003) and the standards in the California State Information Management Methodology (SIMM) as of 2003. Contractor shall meet the following objectives:

bullet

To perform independent and unbiased assessment of the Client’s project with an emphasis on risk management. Such assessment is to include true status of project schedule and cost, performance trends, and accurate forecasts concerning project completion and delivery of the approved business functionality. Contractor will not be required to formally review other contractor’s work.

bullet

To ensure that the oversight and reporting services comply with the requirements of the Information Technology Oversight Framework (ITPOF) as of 2003 (http://www.cio.ca.gov/Government/IT_Policy/pdf/IT_OvrsghtFrmwrkR2-25-04s.pdf#search=oversight&view=FitH&pagemode=none).

bullet

To fulfill additional oversight activities of the Client’s Project, as required and outlined by the Client in the oversight requirements.

bullet

To recommend changes to project management processes that will assist the Client in conducting a successful Client’s project with emphasis on appropriate standards derived from the Project Management Body of Knowledge (PMBOK), 4th edition.

IPOC Responsibilities Overview

The Contractor will be responsible for the formal oversight of project management processes and documentation. The Contractor’s approach to project oversight must:

bullet

Use the ITPOF (as of 2003) as the basis for the contract oversight processes and reporting requirements.

bullet

Use the State Information Management Methodology (SIMM) as of 2003 as the basis for project management methodology standards

bullet

Incorporate Client specific additional oversight requirements and reporting, as specified.

bullet

Initiate the use of key predictive metrics based on the PMBOK, 4th edition.

bullet

Ensure that project management documentation is relevant to Client’s, and is compliant with ITPOF standards for the management of comparable systems development projects.

bullet

On request, provide recommendations to the Client Project Manager regarding fulfillment of their project management responsibilities and best management practices for a large, mission-critical information technology project.

Oversight Management Deliverables

The Contractor will be responsible for managing its own oversight activities, including the effort required in any given month to develop deliverables. Unless otherwise indicated, oversight management products are delivered concurrently to the Project Sponsor and the Client’s Project Director. Changes to deliverable scope or frequency must be approved by the Client’s Project Director.

bullet

Report monthly on oversight activities completed and the status of activities in-progress. The report content shall include the following items:
bullet

“Oversight Activities Completed within the Reporting Period”: oversight activities (evaluations, meetings, reports) accomplished within the reporting period and the names of Contractor staff associated with each activity.

bullet

“Schedule Status”: compares completed oversight tasks and deliverables against oversight activities as scheduled. Includes explanations of schedule variances and recommendations for mitigating the variances.

bullet

“Issues, Problems and Resolutions”: highlights key issues and concerns about the ability to perform oversight activities (such as access to staff or information), as well as mitigation recommendations for emergent problems. The status of previously reported concerns may be reported until resolved.

Content and format of the oversight activity report will be negotiated with the Project Sponsor and Project Director within the first month of this contract. Changes to format and content once established will require approval by the Client Client’s Project Director before enacted.

bullet

Prepare and submit monthly a HAVA timesheet listing the names of Contractor staff working on deliverables for that month and the names and billing amounts for completed deliverables. These are forwarded to the Client Project Director for approval. Note: The HAVA timesheet is not a paid deliverable. It is an invoicing requirement.

Oversight Activity Deliverables

This section describes oversight activities required by the Client’s Project for the duration of Client’s system development and implementation and ending with entry into the “first year of operations” (maintenance and operations (M&O) phase). IPOC services will not be required during the M&O phase (currently called Client’s Phase VII).

The Contractor’s oversight activities will include:

bullet

Monthly production of the mandated Independent Project Oversight Report as specified in the CA IT Project Oversight Framework (ITPOF). The format and content of the IPOR is described in the 2003 ITPOF, Appendix G. The categories of oversight interest specified in the ITPOF are:
bullet

Schedule – completion and approval status for major tasks or milestones

bullet

Resources (Level of Effort) – match of hours/staff to material requirements of major tasks or products.

bullet

Resources (Budget/Cost) – expenditures to budget.

bullet

Quality (Client Functionality) – how adequate the definition and build of required functionality is given the current project phase.

bullet

Quality (Architecture/System Performance) – how adequately the technical architecture has been defined and whether the specified techniques for development and testing are being applied given the current project phase.

bullet

Risks – application of defined risk management processes and the status of identified high criticality risks (new and previously identified).

bullet

Quarterly production of the Project Oversight Review Checklist for high criticality projects, as specified in the ITPOF, Appendix F. The categories of checklist factors in the Project oversight Review Checklist are:
bullet

Planning and Tracking

bullet

Procurement

bullet

Risk Management

bullet

Communication

bullet

System Engineering

bullet

Prepare for and meet a minimum of twice per month for 30 minutes with the Project Manager to discuss project status, and independent oversight concerns and recommendations. Frequency of these meetings may be modified as appropriate to project conditions with approval of the Client’s Project Director. Prepare minutes of the meeting with the Project Manager and deliver the minutes concurrently to the Client’s Project Director and Project Manager for approval by the Project Manager.

bullet

Prepare for and meet with Project Sponsor and Project Director once per month to discuss project status, and independent oversight concerns and recommendations. Prepare minutes of the meetings with Project Sponsor and Project Director and deliver concurrently to Project Sponsor and Project Director.

bullet

Production of a monthly executive summary of project status and oversight findings that includes a graphic representation of the number, classification, criticality and rate of resolution of negative oversight findings.

bullet

Prepare a Final Oversight Report at the end of Phase VI (Deployment and Cutover) detailing the scope of oversight activities performed, the current status of the project, and a description of any outstanding oversight issues or concerns. Include recommendations for resolving concerns as well as lessons learned from Contractor’s perspectives.

bullet

Prepare Ad Hoc Reports, as requested, and in a format approved by the Client. Scope of effort and cost for these deliverables will be individually negotiated with the Client’s Project Director.

Contractor may also avail of the project’s issue and risk management processes to submit IPOC concerns for internal project management. If Contractor elects to raise risks or issues under these processes, Contractor will accept process outcomes as final resolution. Risks or issues raised within monthly management meetings may be escalated separately from the Client’s risk and issue management processes. Participation in the project’s issue and risk management processes are not separate deliverables for billing purposes.

Contract Issue Escalation and Points of Contact

The Client’s Project Director is the initial point of contact for issues regarding this contract. Escalation of unresolved issues is the responsibility of the Client Client’s Project Director. Escalation to the Project Sponsor may be sought if resolution has been attempted and cannot be achieved through the Project Director.

Controls

In completing the tasks within this scope of work, the Contractor will comply with the following standards:

bullet

Contractor shall follow project management industry standards (i.e. PMBOK®, 4th edition). Any adoption of changes to industry standards as represented by subsequent PMBOK editions that would change this contract’s scope or work effort must be approved by the Project Director before being applied to Client’s.

bullet

The State Information Management Manual Project Oversight Framework (ITPOF) and the State Information Management Methodology (SIMM) as of 2003.

Change Control

If unanticipated changes of the Contractor’s approved monitoring plan or schedule are required during the course of the project, the Contractor shall document the changes in writing and submit the change request for approval to the Client’s Project Director. At the time the Contractor or Client identifies an unavoidable change that will require modification of the baseline oversight plan or other issues materially affecting the oversight plan, all work shall stop on the impacted objective until the changes are approved and contract amendment, if required, is fully executed.

 

 

Contact our corporate office today.

 

Home ] Up ]

Send mail to Jubilee Technologies with questions or comments about this web site.